Offshore Project ProgrammeOffshore construction timeline

  • Spring 2010 – pre-construction monitoring starts
  • October 2010 – construction team mobilises at the Port of Ramsgate
  • March 2011 – foundation installation starts
  • July 2011 – installation of offshore substations
  • August 2011 – array cables installation starts
  • Autumn 2011 – installation starts on the first export cable
  • January 2012 –  start of wind turbine installation
  • October 2012 – London Array generates first power
  • December 2012 – Final turbine installed
  • Spring 2013 – project handed over to operations and maintenance team

 