Key construction milestones
Onshore substation
- 2008 – local network diverted slightly to enable substation connection
- Spring 2009 – most pre-construction surveys completed
- Autumn 2009 – earthworks and screening mounds completed
- December 2009 – access roads completed
- July 2010 – control room construction substantially complete
- July to October 2010 – transformer deliveries
- August 2010 – North Wall construction commenced (installation of steel and precast concrete panels)
- September 2010 – internal concrete roads and pavings completed
- November 2010 – Phase One civil construction works completed
- November 2010 – Electrical and mechanical installation started
- March 2011 – Phase two civil works started
- August 2011 to end 2011 – minor works, paving and fencing
- October 2011 – substation commissioning
- March 2012 – landscaping
- Autumn/winter 2011 – installation of first export cable
- Spring/summer 2012 – installation of remaining three export cables
- October 2012 – construction complete
Offshore
- Summer 2010 – offshore construction base built at Port of Ramsgate
- October 2010 – construction team mobilises at Ramsgate
- March 2011 – foundation installation starts
- July- August 2011 – offshore substations installed and array cable installation starts
- Autumn 2011 – installation starts on first export cable
- January 2012 – turbine installation starts
- Spring 2012 – installation starts on remaining export cables
- October 2012 – first power generated
- December 2012 – final turbine installed
- Spring 2013 – project handed over to operations and maintenance team