Onshore substation

Because of the amount of electricity that will be generated (up to 1,000MW)  it is necessary to connect directly into National Grid’s 400kV transmission system to feed the power into the UK’s electricity network.

In June 2005, London Array submitted plans for a new substation, to be built at Cleve Hill near Graveney, about 1km south of the Thames Estuary. The substation would be sited adjacent to the existing Canterbury-Kemsley 400kV overhead line on the north side of Cleve Hill, close to existing farm buildings at Cleve Farm. It would be cut into the north face of Cleve Hill, with a base level of 6.4m Above Ordnance Datum (AOD). Permission to construct the onshore substation was granted following a public inquiry in August 2007.

A small diversion of the existing overhead line was undertaken in 2008 by National Grid as part of the overall design in order to allow the substation to connect into the electricity network. This involved moving it a short distance northwards and replacing three existing towers with new towers of a different design.

A computer generated visualisation of the final design is shown below.

Substation layout